Suppose that the oil price is uncertain and can be either $60/bbl.or $30/bbl.next year with equal probability.Calculate the expected NPV of the project if it is postponed by one year.
A) +50 million
B) -25 million
C) +59 million
D) +47 million
Correct Answer:
Verified