Magnum Construction contracted to construct a factory building for $545,000.The company started during 2012 and was completed in 2013.Information relating to the contract is as follows:
20122013 Costs incured during the year 310,000170,000 Estinated additional cost to complete 165,000 Billings during the year 280,000285,000 Cash collections during the year 260,000305,000\begin{array} { | l | c | c | } \hline & \mathbf { 2 0 1 2 } & \mathbf { 2 0 1 3 } \\\hline \text { Costs incured during the year } & \mathbf { 3 1 0 , 0 0 0 } & \mathbf { 1 7 0 , 0 0 0 } \\\hline \text { Estinated additional cost to complete } & 165,000 & \cdots \\\hline \text { Billings during the year } & 280,000 & 285,000 \\\hline \text { Cash collections during the year } & 260,000 & 305,000 \\\hline\end{array}
Required:
Record the preceding transactions in Magnum's books under completed-contract and the percentage of completion methods.Determine amounts that will be reported on the balance sheet at the end of 2012.

Correct Answer:

verifed

Verified

None...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents