A Company Runs an Assembly Line Two Shifts a Day;

Question 68

Essay

A company runs an assembly line two shifts a day; however,the first shift runs the line 7.5 hours and the second shift runs the line 9 hours.The machine has a maximum output of 120 units per hour.Over the last 28 shifts,the first shift averaged 825 units a shift and the second shift averaged 972 units.Which shift better utilizes the machine?

Correct Answer:

verifed

Verified

First shift utilization = 825 units per ...