Compute the slack for the following project.
Activity A has a duration of 4 days and no predecessor.
Activity B has a duration of 2 days and has A as a predecessor.
Activity C has a duration of 2 days and has A as a predecessor.
Activity D has a duration of 3 days and has B as a predecessor.
Activity E has a duration of 4 days and has C as a predecessor.
Activity F has a duration of 1 day and has D and E as predecessors.

Correct Answer:

verifed

Verified

blured image Activity A slack = 0 - 0 = 0 ...