Which is not true about an activity in a network diagram?
A) Each activity has four parameters
B) Every activity has slack
C) Activity duration times are assumed to be know exactly
D) Delaying activities on the critical path delay the project
E) Noncritical activities have slack
Correct Answer:
Verified
Q45: Describe the time,cost,and scope constraints related to
Q46: Which project management tool introduces uncertainty into
Q47: Which is not a general risk category
Q48: An approach to reduce the amount of
Q49: When computing the expected time for a
Q51: List five PRIMARY characteristics of a project.
Q52: The amount of leeway each activity has
Q53: Project risk can be grouped into four
Q54: Activity 7 is directly preceded by two
Q55: Which of the following is not a