Which of the Following Is True About Work Breakdown Structure

Question 56

Multiple Choice

Which of the following is true about work breakdown structure?


A) It is generally created during the executing process of a project.
B) A word processor is the best software package to create work breakdown structures.
C) Work breakdown structures are used only to plan and list the tasks a team must complete.
D) Gantt charts are generally used to show work breakdown structures.

Correct Answer: