Which of the following describes a project?
A) A temporary activity undertaken to create a unique product, service, or result.
B) The application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project.
C) Any measurable, tangible, verifiable outcome, result, or item that is produced to complete a project or part of a project.
D) Key dates by which a certain group of activities must be performed.
Correct Answer:
Verified
Q38: What are project deliverables?
A) A temporary endeavor
Q45: What is the number one reason that
Q48: Who is the person or group who
Q50: Who are individuals and organizations actively involved
Q51: What is an internal department that oversees
Q52: What are specific factors that can limit
Q52: Who are individuals and organizations actively involved
Q53: What are quantifiable criteria that must be
Q57: What are factors considered to be true,
Q60: What statement links the project to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents