Which one of the following will decrease the net present value of a project?
A) increasing the value of each of the project's discounted cash inflows
B) moving each of the cash inflows back to a later time period
C) decreasing the required discount rate
D) increasing the project's initial cost at time zero
E) increasing the amount of the final cash inflow
Correct Answer:
Verified