Microdash Company uses the high-low method to analyze mixed costs.The following information relates to the production data for the first six months of the year.
What is the estimated total cost at an operating level of 8,000 hours?
A) $9,500.
B) $9,835.
C) $10,135.
D) $10,075.
Total cost = $875 + (8,000 x $1.15) = $10,075
Correct Answer:
Verified
Q63: Which of the following is not one
Q64: If the coefficient of correlation between two
Q65: Sterling Glass Company uses the high-low method
Q66: Sterling Glass Company uses the high-low method
Q67: A range around the regression line within
Q70: The R-squared in a satisfactory regression should
Q71: Sterling Glass Company uses the high-low method
Q72: Which of the following cannot be influenced
Q73: Microdash Company uses the high-low method to
Q78: Cost estimation includes all of the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents