Courts Will Generally Enforce Liquidated Damages Clauses

Question 31

Multiple Choice

Courts will generally enforce liquidated damages clauses:


A) if the specified damages amount to a penalty.
B) provided the damages specified are closely related to the actual damages.
C) if the damages specified amount to a forfeiture.
D) provided exemplary damages are deemed an inadequate remedy.

Correct Answer: