One of the primary jobs of a project manager is to manage the trade-offs associated with the project.Which of the following is NOT one of the basic classifications of project priorities?
A) Profit
B) Cost
C) Time
D) Performance
E) All of these are basic classifications
Correct Answer:
Verified