Which model reviews projects over a long horizon and measures the results of major activities taken to support the overall vision,mission,and goals of the organization? This model helps answer two questions: "Did we select the right projects?" and "Did the project contribute to the long-range strategic direction of the firm?"
A) Phase gate.
B) Project office.
C) Maturity.
D) Retrospective and lessons learned.
E) Balance scorecard.
Correct Answer:
Verified
Q23: The balanced scorecard model differs from project
Q24: When considering the phase gate review process,gate
Q25: It is well established that project-driven companies
Q26: The first appearance of standard approaches to
Q27: The _ phase of the phase-gated process
Q29: An established process of managing projects that
Q30: Phase gates provide an in-depth review of
Q31: The centralized management of projects to ensure
Q32: Project _ can be defined as a
Q33: The _ review process can be defined
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents