Which of the following is NOT one of the growth levels in the Organizational Project Management Maturity Model (OPM3TM) ?
A) Repeatable (formal application of project management) .
B) Defined (institutionalization of project management) .
C) Managed (management of project management system) .
D) Expanded (expansion of project management system) .
E) Optimized (optimization of project management system) .
Correct Answer:
Verified
Q12: The term that can be defined as
Q13: The importance of the increase in project
Q14: The centralized management of projects to ensure
Q15: Typical activities of project oversight cover which
Q16: At the organizational level,all of the following
Q18: During which of the following phase gates
Q19: The purpose of _ is to enable
Q20: The in-depth review of individual projects at
Q21: The project _ is responsible for the
Q22: In which of the following Project Management
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents