Noah Construction Company Is Building a Large Complex for a Contract

Question 71

Multiple Choice

Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project estimated to cost $4,000,000 and the following information is available:
($ in thousands)   Year 1  Year 2  Year 3  Costs incurred $1,000$1,500$1,250 Estimated completion costs $3,000$1,500$10 Billings $750$1,750$2,500 Cash collected $500$1,500$3,000\begin{array}{llll}(\$ \text { in thousands) } & \text { Year 1 } & \text { Year 2 } & \text { Year 3 }\\\text { Costs incurred } & \$ 1,000 & \$ 1,500 & \$ 1,250 \\\text { Estimated completion costs } & \$ 3,000 & \$ 1,500 & \$ 10 \\\text { Billings } & \$ 750 & \$ 1,750 & \$ 2,500 \\\text { Cash collected } & \$ 500 & \$ 1,500 & \$ 3,000\end{array}
-Using the percentage-of-completion method of revenue recognition,how much income is recognized in Year 3?


A) $375,000
B) $625,000
C) $1,000,000
D) $1,250,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents