In a Work Breakdown Structure the ________ Is the Focal

Question 59

Short Answer

In a work breakdown structure the ________ is the focal point because all budgets, work assignments, time, cost, and technical performance come together at that point.

Correct Answer:

verifed

Verified

cost account
Explanation: The ...