Project network logic errors include which of the following?
A) Activities with less than 1 day duration
B) Sequences such as "if test successful build prototype, if failure redesign"
C) A sequence such as B succeeds A, C succeeds B, A succeeds C
D) Both B and C are network logic errors
E) A, B, and C are all network logic errors
Correct Answer:
Verified
Q26: Which of the following correctly calculates the
Q28: Typically an activity on a project network
Q29: A(n) _ is an element in the
Q30: Nodes on an AON project network represent:
A)An
Q32: If testing cannot be completed any earlier
Q33: Activities that can take place at the
Q34: Using a special color copy machine for
Q35: A _ is an activity that has
Q36: Which of the following will correctly calculate
Q59: The activity time estimates used to build
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents