Which of the following is not one of the basic rules to follow when developing project networks?
A) An activity cannot begin until all preceding activities have been completed
B) Each activity must have a unique identification number
C) Conditional statements are allowed but looping statements are not allowed
D) An activity identification number must be larger that that of any preceding activities
E) Networks flow from left to right
Correct Answer:
Verified
Q6: The critical path in a project network
Q7: When translated into a project network, a
Q10: Arrows on an AON project network represent:
A)An
Q10: On a project network, the activity times
Q11: Part of a project is to Develop
Q13: _ activities are to be completed immediately
Q19: An activity that has more than one
Q19: _ activities must be completed immediately before
Q20: The forward pass in project network calculations
Q51: Which of the following correctly calculates the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents