He Earned Value of a Project Is The

Question 4

Multiple Choice

he earned value of a project is the:


A) Project cost to date adjusted for project scope changes
B) Total project cost to date
C) Cost incurred minus the planned cost
D) Percent of the original budget that has been earned by actual work
E) None of these are correct

Correct Answer: