Question 19

Multiple Choice

A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a:


A) Project schedule control chart
B) Gantt chart
C) PERT chart
D) Network diagram
E) Milestone chart