Activity D has an optimistic time of 3 days, a pessimistic time of 9 days, and a most likely time of 4 days.Determine its expected time and variance.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q89: What is the estimated standard deviation in
Q90: Determine the amount of slack in each
Q91: Prepare a crashing plan for the following
Q92: Given the network diagram below, determine the
Q93: What is the estimated expected (mean) time
Q95: The expected duration of this project is:
A)12
B)17
C)20
D)36
E)77
Q96: The expected duration of this project is:
A)13
B)15
C)20
D)52
E)81
Q97: The critical path for the network shown
Q98: What is the probability that this project
Q99: A project has the activities and activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents