A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?
A) It specifies the relationships in the CPM network of activities.
B) It provides useful timing information.
C) It includes cost information.
D) It is the probability information required in the final step of CPM.
E) None of these
Correct Answer:
Verified
Q45: A simple project listing of five activities
Q45: An advantage of a pure project where
Q46: A series of projects that are organized
Q46: In a Gantt chart, the horizontal axis
Q47: What is a work breakdown structure?
A) A
Q48: You have been placed in charge of
Q50: PERT is an abbreviation for which of
Q51: You are looking at a chart that
Q52: Some of the advantages of a functional
Q61: For an activity in a CPM analysis,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents