Which of the following are accurate statements concerning MPS,MRP and capacity requirements planning (CRP) ?
I.CRP is equivalent to a master production schedule (MPS) .
II.CRP is needed to determine if an MPS is feasible.
III.CRP is an input to MRP.
IV.Planned-order releases from MRP are the inputs for CRP.
A) I and II
B) I, II, and III
C) II and IV
D) II, III, and IV
E) I, II, III, and IV
Correct Answer:
Verified
Q52: The MRP input stating which end items
Q55: Pegging is used primarily for which one
Q61: If the firm is using lot size
Q62: What is the economic part-period (EPP)for ordering
Q63: What is the lot size for the
Q65: What is the net requirement for Whatzats
Q67: If 40 Ps are needed, and on-hand
Q67: When should an order for Wherezats be
Q68: A report that compares known and expected
Q69: If 17 Ps are needed,and no on-hand
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents