There are four activities on the critical path,and the standard deviations for their durations are 1,2,4,and 2 days.The standard deviation of the duration of the critical path is:
A) 3
B) 5
C) 9
D) 16
E) 25
Correct Answer:
Verified
Q60: The main determinant of the way PERT/CPM
Q61: In the probabilistic approach to precedence network
Q62: The principal advantage a Gantt chart has
Q63: The project management technique that is repeated
Q64: A relatively simple tool for planning and
Q66: A PERT/CPM activity has an optimistic duration
Q67: Concerning PERT and CPM,which of the following
Q68: Which of the following is used to
Q69: In a precedence network the critical path
Q70: In precedence network analysis,knowing the slack time