A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data: Approximately how long did it take to produce the first four units?
A) 15 hours
B) 16 hours
C) 18 hours
D) 20 hours
E) 21 hours
Correct Answer:
Verified