Use the Earned Value Table for Project Makeready to Calculate
Question 68
Question 68
Multiple Choice
Use the earned value table for Project Makeready to calculate the estimated cost to completion. Activity Irstall fixtures Refinish floors Replace doors Complete tiling Irstall back door Landscaping Monthly Plarn Monthly Act 7325325550142505508005502185350435550282751,2001,4751,100355658751,4401,65042225200425550493503501,100 plan 5756356251,7651,1005505,2508 Complete 100%100%100%80%70%25%
A) $4,285 B) $5,250 C) $6,050 D) $7,645
Correct Answer:
Verified
Unlock this answer now Get Access to more Verified Answers free of charge