Use the Earned Value Table to Determine the Cost Performance
Question 59
Question 59
Multiple Choice
Use the earned value table to determine the cost performance index given the indicated state of the project. Activity A B CDEFG Monthly Plan Monthly Act 585085090010350400750650151251,2751,4001,3502065028003,4503,875254,5006805,1804,780303504001253001,1758503587512002,0752,000 Plan 1,2005251,9257,6501,0801,0001,50014,880% Complete 100%100%100%95%75%80%45%
A) 0.89 B) 0.92 C) 1.09 D) 1.13