Take the factors considered by earned value analysis and subtract those considered by project S-curves.The factor(s) you have remaining are:
A) Performance and cost.
B) Cost and schedule.
C) Time.
D) Performance.
Correct Answer:
Verified
Q29: It is possible to measure:
A)Only positive deviations
Q30: The earned value divided by the actual,cumulative
Q31: Positive variance on an S-curve is not
Q32: Take the factors considered by earned value
Q33: It is possible to measure both positive
Q35: What are drawbacks to a pure S-curve
Q36: One strength of S-curve analysis is that
Q37: Earned value management is also known as:
A)The
Q38: Planned value is:
A)The total budget for the
Q39: The classic S-curve is a plot of