Project Goal Setting Includes Setting a Baseline Plan,which Is Predicated

Question 20

Multiple Choice

Project goal setting includes setting a baseline plan,which is predicated on:


A) The progress measurement.
B) An accurate work breakdown structure.
C) The type of gap analysis the project team plans to use.
D) The budget and schedule limitations.

Correct Answer: