A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed while constrained by the four worker limitation?
A) 68 days
B) 70 days
C) 66 days
D) 72 days
Correct Answer:
Verified
Q68: If resources have been over-allocated,the loading table
Q69: A project consisting of six activities
Q70: A project consists of eleven activities
Q71: A project consists of eleven activities
Q72: A resource loading table is created through
Q74: A project consists of eleven activities
Q75: A project consists of eleven activities
Q76: The first step in the resource leveling
Q77: Because resource management is typically a multivariate,combinatorial
Q78: A project consists of six activities
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents