Create a Resource Loading Chart Using Early Start Times for the Project

Question 22

Essay

Create a resource loading chart using early start times for the project described by this table.
 Activity  Tirne  Predecessor  Task A144B25C4 A5D9 B4E8C5F2C3G3D2H5 F,G4K1E3L13H, K4\begin{array} { | l | l | l | l |} \hline \text { Activity } & \text { Tirne } & \text { Predecessor } & \text { Task } \\\hline \mathrm { A } & 14 & - & 4 \\\hline \mathrm { B} & 2 & - & 5 \\\hline \mathrm { C } & 4 & \mathrm {~A} & 5 \\\hline \mathrm { D } & 9 & \mathrm {~B} & 4 \\\hline \mathrm { E } & 8 & \mathrm { C } & 5 \\\hline \mathrm { F } & 2 & \mathrm { C } & 3 \\\hline \mathrm { G } & \mathbf { 3 } & \mathrm { D } & 2 \\\hline \mathrm { H } & 5 & \mathrm {~F}, \mathrm { G } & 4 \\\hline \mathrm { K } & 1 & \mathrm { E } & 3 \\\hline \mathrm { L } & 13 & \mathrm { H } , \mathrm {~K} & 4 \\\hline\end{array}

Correct Answer:

verifed

Verified

The early start times appear in this tab...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents