Solved

Use the Project Information in the Table to Resolve Resource

Question 98

Multiple Choice

Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.The critical chain does NOT pass through:  Activity  Predecessor  Length  Resource  Activity  Predecessor  Length  Resource  A 11PDC13PB A 7ME12XCB8 W FE14M\begin{array} { | l | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Resource } & \text { Activity } & \text { Predecessor } & \text { Length } & \text { Resource } \\\hline \text { A } & - & 11 & P & D & C & 13 & P \\\hline B & \text { A } & 7 & M & E & - & 12 & \mathbf { X } \\\hline \mathbf { C } & \mathrm { B } & 8 & \mathrm {~W} & \mathrm {~F} & \mathrm { E } & 14 & \mathrm { M } \\\hline\end{array}


A) Activity A.
B) Activity F.
C) Activity E.
D) Activity D.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents