A complex project that is managed using a top-down,bottom-up approach to network diagrams means that:
A) Management's top-down portion of the network contains the greatest detail.
B) Top management does not have a basis for understanding the actual development of the project.
C) The top tier summary network does not give top management the basis for understanding the actual development of the project.
D) The bottom level information cannot be understood by those performing the actual work.
Correct Answer:
Verified
Q80: An activity on an arrow network:
A)Cannot have
Q81: Networks would NOT be well suited for:
A)Planning
Q82: For large projects,network diagrams are more useful
Q83: Sketch the network described in the
Q84: Research has shown that,in general:
A)There is a
Q86: What are the strengths and weaknesses of
Q87: Most activity estimations using PERT methods lead
Q88: Mick has a project consisting of
Q89: Determine early start and early finish times
Q90: Mick has a project consisting of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents