Use the information in the table to determine the slack time for Activity B.
A) 6 days
B) 4 days
C) 2 days
D) 0 days
Correct Answer:
Verified
Q86: The PERT technique assumes that durations are
Q87: Float is always measured in exactly the
Q88: Negative float exists when a project's critical
Q89: The BEST candidate activities for shortening the
Q90: Use the values in the table
Q92: Use the values in the table
Q93: A project's duration can be reduced by:
A)Shortening
Q94: What is the float start time
Q95: An MBA student laboriously calculated the
Q96: What is the slack time for