Solved

Use the Information in the Table to Determine the Late

Question 67

Multiple Choice

Use the information in the table to determine the late finish time for Activity B.  Early  Early  Late  Late  Task  Predecessor  Duration  Start  Firish  Start  Firish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & \mathrm { -- } & \mathbf { 8 } & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf { 8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}


A) Day 17
B) Day 20
C) Day 23
D) Day 26

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents