A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?
A) 1.33 days
B) 1.56 days
C) 1.25 days
D) 1.75 days
Correct Answer:
Verified
Q53: What are three methods of duration estimation
Q54: You must know the mean of an
Q55: Use the values in the table
Q56: What is the underlying theory to the
Q57: What is the early finish time
Q59: Use the values in the table
Q60: What is the late finish time
Q61: A project has the precedence requirements
Q62: What is the slack time for
Q63:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents