Solved

A Gentleman Farmer Maniacally Works on Academic Projects to Raise

Question 58

Multiple Choice

A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?  Optimistic Most Likely  Pessimistic  Activity  time  time  time  Predecessor  Corner Posts 456 String Line 789 Dig Holes 101214 Corner Posts  Plant Posts 111417 String Line  Weld Top Bar 81114 String Line  Dig Holes, Plant  Paint 91113 Posts  Tack Wire 91216 Weld Top Bar \begin{array}{|l|l|l|l|l|}\hline&\text { Optimistic} & \text { Most Likely } & \text { Pessimistic }\\ \text { Activity } & \text { time } & \text { time } & \text { time } & \text { Predecessor }\\ \hline \text { Corner Posts } & 4 & 5 & 6 & - \\\hline \text { String Line } & 7 & 8 & 9 & -- \\\hline \text { Dig Holes } & 10 & 12 & 14 & \text { Corner Posts } \\\hline \text { Plant Posts } & 11 & 14 & 17 & \text { String Line } \\\hline \text { Weld Top Bar } & 8 & 11 & 14 & \text { String Line } \\\hline & & & & \text { Dig Holes, Plant } \\ \text { Paint } & 9 & 11 & 13 & \text { Posts } \\\hline \text { Tack Wire } & 9 &12& 16& \text { Weld Top Bar } \\\hline\end{array}


A) 1.33 days
B) 1.56 days
C) 1.25 days
D) 1.75 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents