A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?
A) 32 days
B) 33 days
C) 34 days
D) 35 days
Correct Answer:
Verified
Q47: What is the early start time
Q48: Q49: Laddering is a technique that allows the Q50: What is the late start time Q51: Use the information in the table Q53: What are three methods of duration estimation Q54: You must know the mean of an Q55: Use the values in the table Q56: What is the underlying theory to the Q57: What is the early finish time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents