With a maturity risk of 0.3,a complexity risk of 0.4,and a dependency risk of 0.5,the probability of failure is:
A) About 0.3.
B) About 0.4.
C) About 0.5.
D) About 0.6.
Correct Answer:
Verified
Q21: A serious risk factor probably has:
A)A high
Q22: One source of information on future risks
Q23: A method for conducting risk factor identification
Q24: Your project team members do not have
Q25: The marketing team would develop the advertising
Q27: A project under strict terms and conditions
Q28: This scenario best describes a workaround:
A)Responding to
Q29: The inability of a company to accurately
Q30: A method for conducting risk factor identification
Q31: A project team assesses their primary risk