Expected Commitments from Other Departments in Support of the Project

Question 10

Multiple Choice

Expected commitments from other departments in support of the project would most likely be detailed in the:


A) Approach section of the SOW.
B) Risks and concerns section of the SOW.
C) Acceptance criteria section of the SOW.
D) Resource requirements section of the SOW.

Correct Answer:

verifed

Verified