Solved

If the Following Project Must Be Completed by Day 18 \le

Question 24

Multiple Choice

If the following project must be completed by day 18 at minimum cost how do we change the LP model?  If the following project must be completed by day 18 at minimum cost how do we change the LP model?   A) Enter 18 in cell E14. B) Add a constraint that E14  \le  18. C) Make cell E14 the target cell. D) Add a constraint that E14 = 18.


A) Enter 18 in cell E14.
B) Add a constraint that E14 \le 18.
C) Make cell E14 the target cell.
D) Add a constraint that E14 = 18.