For an activity in a CPM analysis,the Early Start time is 8 and the Late Start time is 10.Which of the following statements is true?
A) The Late Finish is 12
B) The Early Finish is 10
C) The slack for this activity is 2
D) The duration of this activity is 2
E) The activity is on the critical path
Correct Answer:
Verified
Q41: Which of the following is a graphic
Q43: You have just been assigned to oversee
Q45: An advantage of a pure project where
Q46: In a Gantt chart, the horizontal axis
Q49: project starts out as which of the
Q52: company must perform a maintenance project consisting
Q53: simple project listing of five activities,their predecessors,and
Q56: simple project listing of five activities and
Q57: simple project listing of five activities,their predecessors,and
Q59: For an activity in a CPM analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents