When the Major Focus of a Project Must Be on the In-Depth

Question 40

Multiple Choice

When the major focus of a project must be on the in-depth application of a technology rather than on minimizing cost,meeting a specific schedule or achieving speedy response to change,the __________ organizational form is apt to be the form of choice.


A) strong
B) weak
C) functional
D) mixed