Although the contract called for the delivery of three manuals,the writer had put so much effort into the first two that the buyer agreed to pay the whole contract price,$3000,for the two instead of the three manuals.Which of the following stops the buyer from later suing the writer for breach of contract and demanding the completion of the third manual?
A) doctrine of quantum meruit
B) no consideration given by the writer
C) promissory (equitable) estoppel
D) He only has to pay a reasonable price for the work done.
E) He doesn't have to pay anything because the job was not completed, and so he can even get back what he paid.
Correct Answer:
Verified
Q45: Berman made a documentary on the life
Q46: Joe contracted with Sam,agreeing to pay Sam
Q47: George contracted with Bob to have a
Q48: With regard only to the requirement of
Q49: An agreement for the purchase and sale
Q51: The ad in the Real Estate Weekly
Q52: X contracted with Z.X promised to pay
Q54: Which of the following shows the use
Q55: The owner of a large restaurant wanted
Q74: Which of the following is false with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents