The Beta distribution is useful in network analysis because it ________.
A) provides formulas for calculating the activity mean and variance
B) can be approximated by a normal distribution
C) provides probability estimates for project completion time
D) requires only three time estimates to describe uncertain activity duration
Correct Answer:
Verified
Q27: Implementing critical path analysis is faced with
Q28: A resource-leveled schedule would have all of
Q29: Which of the following is not a
Q30: Gantt project charts are useful for all
Q31: Which of the following makes performance a
Q33: Which of the following attributes is not
Q34: The amount of time an activity can
Q35: Monte Carlo simulation of project networks is
Q36: A major weakness with project completion time
Q37: Which of the following is not considered
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents