Solved

Which of the Following Is Not True About a Critical

Question 26

Multiple Choice

Which of the following is not true about a critical path in a project network with certain activity times?


A) Activities on the critical path have the least slack.
B) The longest activity in the project must lie on the critical path.
C) There can be several critical paths in a project network.
D) The first activity in the network is always on the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents