Which of the following is not true about a critical path in a project network with certain activity times?
A) Activities on the critical path have the least slack.
B) The longest activity in the project must lie on the critical path.
C) There can be several critical paths in a project network.
D) The first activity in the network is always on the critical path.
Correct Answer:
Verified
Q21: For a project with uncertain activity times,
Q22: Projects are terminated for all of the
Q23: The four sequential stages of team development
Q24: Which of the following is not considered
Q25: Which one of the following allows the
Q27: Implementing critical path analysis is faced with
Q28: A resource-leveled schedule would have all of
Q29: Which of the following is not a
Q30: Gantt project charts are useful for all
Q31: Which of the following makes performance a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents