All of the following accurately describe earned value management EXCEPT:
A) It is used to make predictions concerning the project schedule and cost control until the project's conclusion.
B) It enables a project team to understand progress in terms of both cost and schedule.
C) It is good for performance reporting but not for forecasting
D) It is used as a decision-making tool.
Correct Answer:
Verified
Q34: This Agile project reporting tool is useful
Q35: Some organizations rely upon a formal group
Q36: Work to be performed can come from
Q37: The Budget at Completion (BAC)is the sum
Q38: During schedule and cost control,when comparing performance
Q39: Change control is a process wherein change
Q41: Describe the three different categories of risk
Q42: Define integrated change control and briefly explain
Q43: Describe how you would adopt a balanced
Q44: Your most recent project performance report indicates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents