_______ Is the PMBOK Process That Identifies Those Project Needs

Question 22

Multiple Choice

_______ is the PMBOK process that identifies those project needs that can be met by acquiring products and services from outside suppliers,determines what to purchase or acquire,and finalizes when and how to do so.


A)  Define supply chain. 
B)  Plan procurement management. 
C)  Schedule procurements. 
D)  Negotiate contracts