A milestone is a typical measuring point used when establishing cost control.Which of the following does NOT accurately describes the use of cost control milestones?
A) Project managers can use their cash flow projections to determine the funding needed to reach each milestone.
B) Project managers and sponsors often decide the number of milestones jointly.
C) Milestones are often identified in the project charter.
D) Milestones are developed during risk planning.
Correct Answer:
Verified
Q36: The cost management plan provides guidelines to
Q37: Q38: A project manager needs to ensure that Q39: All of the following items describe an Q40: Which of the following terms best describes Q41: Discuss how the accuracy of cost estimates Q42: Describe several sources of uncertainty in estimating Q44: Events discovered during Identify Risks that may Q45: Describe analogous,parametric and bottom-up estimating,and briefly discuss Q46: "Unknown unknowns" are unexpected events which can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents