The documentation of a project cost estimate generally requires substantial supporting detail to include all of these EXCEPT:
A) a description of scope.
B) management reserve needs
C) the estimating methods and a range of possible outcomes.
D) assumptions and constraints.
Correct Answer:
Verified
Q19: The project scope does not come into
Q20: Inflating the value of future revenue and
Q21: The _is the approved budget,usually in a
Q22: The process of developing an approximation of
Q23: There are many causes of variation in
Q25: Which estimating technique uses a statistical relationship
Q26: Value engineering is aimed at increasing the
Q27: Projects often include indirect costs that are
Q28: Which estimating technique decomposes the work into
Q29: Which estimating technique uses a statistical relationship
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents