Estimate Cost is the process of developing an approximation of the monetary resources needed to complete project activities.
Correct Answer:
Verified
Q3: On agile projects,project managers may use rolling
Q4: Most projects will employ bottom-up estimating at
Q5: Regardless of what method is used to
Q6: Both normal and special cause variation add
Q7: Project managers should not lie to themselves
Q9: Plan Cost Management is the process to
Q10: Typically,expedited costs are preferred over regular costs.
Q11: A contingency reserve is money assigned to
Q12: On small projects,the cost management plan may
Q13: Analogous estimating is the most detailed,time consuming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents