Which of the following statements correctly describes the critical path?
A) The sequence of activities that represents the shortest path through the project network.
B) It determines the latest possible end date of the project.
C) It consists only of activities with zero float (slack) .
D) It consists only of activities with lag times
Correct Answer:
Verified